Planning of human resources from the simulation of the construction process in BIM 5D models

Authors

DOI:

https://doi.org/10.18041/entramado.2018v14n1.27141

Keywords:

BIM 5D, building information modeling, construction, human resources planning, manpower

Abstract

The human resources planning of a construction project is an activity of great importance for the successful development of construction activities. It is a complex task that requires automated tools and methodologies that allow the optimization of variables related to time and costs. Building Information Modeling (BIM) is a digital database that allows to obtain a virtual replication constructive process from five variables: i) time; ii) costs; and three dimensions x, y, z; model that is known as BIM 5D. In this paper, it proposes a methodology for the planning of human resources based on the simulation of the BIM 5D construction processes. A set of techniques for the planning of the human resource in construction projects is presented and planning of a case study is carried out from the BIM 5D approach. Taking in account the results, it formalized a method for human resource planning. Compared to other methodologies, it presents advantages such as automation and the possibility of evaluating different alternatives in reduced times.

Downloads

Download data is not yet available.

Author Biographies

  • Jherson Jhadir Bohórquez-Castellanos, Universidad Industrial de Santander, Bucaramanga – Colombia.

    Maestría en Ingeniería Civil, Universidad Industrial de Santander, Bucaramanga – Colombia. 

  • Hernán Porras-Díaz, Universidad Industrial de Santander, Bucaramanga – Colombia. 

    Doctor en Ingeniería Telemática, Universidad Politécnica de Madrid. Magíster en Gestión Tecnológica, Universidad Pontificia Bolivariana.  Rector de la Universidad Industrial de Santander, Bucaramanga – Colombia. 

  • Omar Giovanny Sánchez-Rivera, Universidad Industrial de Santander, Bucaramanga – Colombia

    Doctorando en Ingeniería - Gestión de Desarrollo Tecnológico, Universidad Industrial de Santander. Profesor Cátedra, Universidad Industrial de Santander, Bucaramanga – Colombia.

  • María Camila Mariño-Espinel, Universidad Industrial de Santander, Bucaramanga - Colombia

    Ingeniería Civil de la Universidad Industrial de Santander, Bucaramanga - Colombia. 

References

ASHCRAFT, Howard W. Building Information Modeling: A Framework for Collaboration. In: Construction Lawyer. 2008. Vol. 28, no. 3, p. 1–14. https://www.hansonbridgett.com/-/media/Files/Publications/bim_building_information_modeling_a_framework_for_collaboration.pdf

2. AZHAR, Salman. Building Information Modeling (BIM): Trends, Benefits, Risks, and Challenges for the AEC Industry. In: Leadership and Management in Engineering. 2011. Vol. 11, no. Bazjanac 2006, p. 241–252. https://doi.org/10.1061/(ASCE)LM.1943-5630.0000127

3. BOHÓRQUEZ CASTELLANOS, Jherson Jhadir. Planificación de recursos humanos para la construcción de estructuras en concreto reforzado, con base en modelos BIM 5D. Trabajo de grado Ingeniero Civil. Universidad Industrial de Santander. Facultad de Ingenierías Fisicomecánicas. Escuela de Ingeniería Civil. 2016. 50 p.

4. BRAIMAH, Nuhu. Understanding Construction Delay Analysis and the Role of Preconstruction Programming. In: Journal of Management in Engineering. 2014. Vol. 30, no. 5, p. 4014023. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000216

5. BYNUM, Patrick. ISSA, Raja. R. A. y Olbina, Svetlana. Building information modeling in support of sustainable design and construction. In: American Society of Civil Engineers. 2013. Vol. 139, no. 1, p. 24–34. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000560

6. CHONG, Heap Yih. LOPEZ, Robert. WANG, Jun. WANG, Xiangyu y ZHAO, Zeyu. Comparative Analysis on the Adoption and Use of BIM in Road Infrastructure Projects. In: Journal of Management in Engineering. November, 2016. Vol. 32, p. 1–13. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000460

7. CRUZ-MACHADO, Virgílio y ROSA, Pedro. Modelo de planificación basado en construcción ajustada para obras de corta duración. En: Informacion Tecnológica. 2007. Vol. 18, no. 1, p. 107–118. https://scielo.conicyt.cl/scielo.php?script=sci_abstract&pid=S0718-07642007000100015&lng=es&nrm=iso&tlng=en

8. ELHAKEEM, Ahmed y HEGAZY, Tarek. Graphical Approach for Manpower Planning in Infrastructure Networks. In: Journal of Construction Engineering and Management. 2005. Vol. 131, no. February, p. 168–175. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:2(168)

9. GOMAR, Jorge E., HAAS, Carl T. y MORTON, David P. Assignment and Allocation Optimization of Partially Multiskilled Workforce. In: Journal of Construction Engineering and Management. 2002. Vol. 128, no. April, p. 103–109. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:2(103)

10. HEGAZY, Tarek. ELHAKEEM, Ahmed y ELBELTAGI, Emad. Distributed Scheduling Model for Infrastructure Networks. In: Journal of Construction Engineering and Management. 2004. Vol. 130, no. April, p. 160–167. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:2(160)

11. HO, Paul. H. K. Forecasting Construction Manpower Demand by Gray Model. In: Journal of Construction Engineering and Management. Diciembre, 2010. Vol. 136, no. December, p. 1299–1305. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000238

12. LU, W., PENG, Y., SHEN, Q., & LI, H. (2012). A Generic Model for Measuring Benefits of BIM as a Learning Tool in Construction Tasks. In: Journal of Construction Engineering and Management, 139(February), 441. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000585

13. MALONEY, William. F. Strategic planning for human resource management in construction. In: Journal of Management in Engineering. 1997. Vol. 13, no. 3, p. 49–56. https://doi.org/10.1061/(ASCE)0742-597X(1997)13:3(49)

14. MEJÍA AGUILAR, Guillermo. HERNÁNDEZ C., Triny Carolina. Seguimiento de la productividad en obra: técnicas de medición de rendimientos de mano de obra. En: Revistas UIS Ingenierías. 2007. Vol. 6, no. 2, p. 45-59. http://revistas.uis.edu.co/index.php/revistauisingenierias/article/view/405

15. NEPAL, Madhav Prasad., STAUB-FRENCH, Sheryl. POTTINGER, Rachel y ZHANG, Jiemin. Ontology-based feature modeling for construction information extraction from a Building Information Model. In: Journal of Computing in Civil Engineering. 2013. Vol. 27, no. 5, p. 555–570. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000230

16. NIE, Howard. STAUB-FRENCH, Sheryl y FROESE, Thomas. OLAP-integrated project cost control and manpower analysis. In: Journal of Computing in Civil Engineering. 2007. Vol. 21, no. 3, p. 164–174. https://doi.org/10.1061/(ASCE)0887-3801(2007)21:3(164)

17. PERSAD, Khali R. O’CONNOR, J. T. y VARGHESE, Koshy. Forecastng Engineering Manpower Requirements for Highway Precosntruction Activities. In: Journal of Management in Engineering. Mayo, 1995. Vol. 11, no. 3, p. 41–47. https://doi.org/10.1061/(ASCE)0742-597X(1995)11:3(41)

18. PORRAS-DÍAZ, Hernán. SÁNCHEZ-RIVERA, Omar Giovanny. GALVIS-GUERRA, José Alberto. JAIMEZ-PLATA, Néstor Albeiro y CASTAÑEDA-PARRA, Karen Milady. Tecnologías “Building Information Modeling” en la elaboración de presupuestos de construcción de estructuras en concreto reforzado. En: Entramado. Enero – Junio, 2015. Vol. 11, no. 1, p. 230-249. http://dx.doi.org/10.18041/entramado.2015v11n1.21116

19. PORRAS-DÍAZ, Hernán. SÁNCHEZ-RIVERA, Omar Giovanny. GALVIS-GUERRA, José Alberto. Metodología para la elaboración de modelos del proceso constructivo 5D con tecnologías “Building Information Modeling”. En: Revista Gerencia Tecnológica Informática. Enero – Abril, 2015. Vol. 14, no. 38, p. 59-73. http://revistas.uis.edu.co/index.php/revistagti/article/view/4869

20. QUIROGA LEÓN, César Augusto. Estudio de las ventajas y desventajas de la utilización de modelos BIM 5D y la herramienta Last Planner en la planificación de proyectos de edificación. Universidad Industrial de Santander. Facultad de Ingenierías Fisico-mecánicas. Escuela de Ingeniería Civil. 2015. 68 p.

21. SÁNCHEZ POLANCO, Lina Marithza. Análisis de rendimientos de mano de obra para actividades de construcción-Estudio de caso Edificio J UPB-. Universidad Pontificia Bolivariana. Facultad de Ingeniería Civil. Escuela de ingenierías y administración. 2009. 72 p.

22. SÁNCHEZ RIVERA, Omar Giovanny. Análisis del flujo de caja de la construcción de un proyecto con modelos BIM 5D y dinámica de sistemas. Universidad Industrial de Santander. Facultad de Ingenierías Fisico-mecánicas. Escuela de Ingeniería Civil. 2015.

23. SCHAFFER, Robert J. Manpower Planning-Make a “Moral Contract”. In: Journal of Management in Engineering. 1988. Vol. 4, no. 1, p. 56–59.https://doi.org/10.1061/(ASCE)9742-597X(1988)4:1(56)

24. SHING-TAO, A. Work-Time Model for Engineers. In: Journal of Construction Engineering and Management. March/April, 2001. Vol.127, no 2. p. 163–172. http://ir.lib.ncku.edu.tw/bitstream/987654321/40082/1/3010601701002.pdf&embedded=true

25. SHUJAA, Syed. SHAFIQ, Nasir y KHAMIDI, Mohd Faris. Prospects of Building Information Modeling (BIM) in Malaysian Construction Industry as Conflict Resolution Tool. 2013. In: Journal of Energy Technologies and Policy. Vol. 3, no. March 2016, p. 346–350. https://www.iiste.org/Journals/index.php/JETP/article/view/8582

26. SING, Michael; LOVE, Peter E. D.; EDWARDS, J. y LIU, Junxiao. Dynamic Modeling of Workforce Planning for Infrastructure Projects. In: Journal of Management in Engineering. Noviembre, 2016. Vol. 32, no. 6, p. 1–9.https://doi.org/10.1061/(ASCE)ME.1943-5479.0000463

27. SING, Chun-Pong. LOVE, Peter E. D. y TAM, Chi-Ming. Forecasting the Demand and Supply of Technicians in the Construction Industry. In: Journal of Management in Engineering. Mayo, 2014. Vol. 30, no. 3, p. 1–9. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000227

28. SING, Chun-Pong. LOVE, Peter E. D. y TAM, Chi-Ming. Multiplier Model for Forecasting Manpower Demand. In: Journal of Construction Engineering and Management. 2012. Vol, 138, no. 10, p. 1161–1168. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000529

29. SU, Xing y CAI, Hubo. Enabling Construction 4D Topological Analysis for Effective Construction Planning. In: Journal of Computing in Civil Engineering. Enero, 2016. Vol. 30, no. 1, p. 1–10. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000463

30. SU, Xing y CAI, Hubo. Life Cycle Approach to Construction Workspace Modeling and Planning. In: Journal of Construction Engineering and Management. Julio, 2014. Vol. 140, no. 7. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000855

31. WU, Wei y ISSA, Raja. R. A. Key Issues in Workforce Planning and Adaptation Strategies for BIM Implementation in Construction Industry. Construction Research Congress, mayo, 2014.

32. WONG, James M. W. CHAN, Albert P. C. y CHIANG, Y. H. Modeling and Forecasting Construction Labor Demand: Multivariate Analysis. In: Journal of Construction Engineering and Management. Septiembre, 2008. Vol. 134, no. 9, p. 664–672.https://doi.org/10.1061/(ASCE)0733-9364(2008)134:9(664)

Published

2018-10-11

Issue

Section

Articles

Similar Articles

1-10 of 626

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)